This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

BROWSE PRODUCTS
 

Supplying back-up in the City

Four FG Wilson high voltage standby power units from Dieselec Thistle Generators have been delivered for installation in a data centre in central London following exhaustive load testing at the supplier’s Glasgow headquarters.

The four generators are being installed while the banking facility is ‘live’ and fully operational.

Representatives from contractor Skanska Rashleigh Weatherfoil (SRW) and the end client – a major City institution – travelled to Dieselec Thistle’s Scottish facility to witness five days of continuous testing of the equipment, worth in excess of £3m.

During this process, the four 11kV generators, each capable of delivering 2mVA of power, were run individually at full load for eight hours and then synchronised and run together to deliver the full power.

This rigorous test procedure was essential to demonstrate that the generators, once installed in their central London location, will be capable of delivering consistent, reliable power to maintain their mission critical systems.

“Data centres store huge amounts of very valuable and sensitive information,” explains Pedro Araujo, Dieselec Thistle’s London solutions Director. “They require extreme resilience in their power infrastructure because if they lose power they can lose millions in revenue in a matter of minutes. They see the value in investing in new power generating systems to ensure that this doesn’t happen,” he adds.

Data centres require far higher levels of power than most comparable buildings – often having power densities more than 100 times that of a similar-sized office building. Much of the power is required to run the cooling plant, which is essential to prevent the computer systems from overheating.

So-called ‘witnessed’ live-load testing is increasingly demanded by clients who need absolute assurances that their back-up power supply will safeguard their assets in the event of a mains power cut.

The four new generators replace five old models currently located three basement levels below the client’s building. While these are decommissioned and the new equipment is installed, back-up power is being provided by temporary generators housed in a neighbouring building.

The 50-week project is due for hand-over in November and throughout the project the data centre has remained occupied and fully functioning, with SRW carrying out most of the work out-of-hours.